EU Data Center Maintenance from 2025-10-16 05:00 MST to 2025-10-16 14:37 MST

Scheduled maintenance Portal (EU) API Mobile App Web
2025-10-16 05:00 MST · 9 hours, 37 minutes

Updates

Resolved

RESOLUTION: Ireland Data Center Migration Successfully Completed

Time of Update: 10:30 PM GMT+1 (Total maintenance time: approximately 9 hours and 30 minutes)

We are thrilled to announce that the Ireland Data Center migration has been successfully completed, significantly ahead of the original 1:00 AM GMT+1 schedule!

All services are now online.

We thank you for your patience and understanding during this critical infrastructure upgrade.

If you experience any issues, please contact your usual support channel immediately.

ArmorPoint Ireland Operations

October 16, 2025 · 14:30 MST
Update

We have excellent news regarding the Ireland Data Center migration!

Phase 2 is now officially complete, and we have made significant progress on Phase 3. Our team has been working efficiently and is significantly ahead of the original schedule.

Anticipated Service Restoration

Due to this accelerated progress, we now expect to start restoring services within the next hour!

The remaining time of the originally planned maintenance window (until the initial 1:00 AM GMT+1 E.T.C.) will be used for final, rigorous validation and stability checks to ensure everything is operating at peak performance.

Current Impact Summary

The following services are still temporarily offline but are preparing for restoration:

  • ArmorPoint SIEM Platform
  • ArmorPoint Mobile App access
  • Log collection

As a reminder, your Security Monitoring & Incident Response and EDR Monitoring have remained fully operational throughout this entire process.
We will send the final “All Clear” announcement once all services are fully restored and confirmed stable. Thank you for your patience and flexibility today!

ArmorPoint Ireland Operations

October 16, 2025 · 11:00 MST
Update

This marks the halfway point of our planned migration window, and we’re happy to report excellent progress!

Phase 2 of 3 is now close to completion.

Status: Running ahead of schedule and transitioning to the final phase soon.

Estimated Completion: While we are currently ahead of pace, the estimated completion time remains conservatively set at 1:00 AM GMT+1. This allows us to ensure a thorough and careful validation during the critical final phase before we restore service.

October 16, 2025 · 11:00 MST
Update

We’re pleased to provide a significant update on the Ireland Data Center migration:

Phase 1 of 3 has been completed successfully and we have progressed to Phase 2.

Status: The migration is progressing well and remains on track with our original estimated completion time.

Estimated Completion: The estimated completion time is still approximately 1:00 AM GMT+1.

October 16, 2025 · 08:00 MST
Update

This is a brief check-in regarding the scheduled migration of our Ireland Data Center.

We can confirm that Phase 1 is successfully underway and the migration process is running smoothly and according to plan.

Status: We remain on track.

Estimated Completion: The estimated completion time remains approximately 12 hours from the start (i.e., by 1:00 AM GMT+1).

October 16, 2025 · 06:00 MST
Started

This maintenance is now starting as planned.

October 16, 2025 · 05:00 MST
Scheduled

We will be performing a scheduled migration of our Ireland Data Center today, October 16, 2025, beginning at 1:00 PM GMT+1.

Please Note: The migration window is still expected to last approximately 12 hours.

We understand the importance of clear communication, and we will be continually posting updates on our status page throughout the maintenance window.

What to Expect

During this time, the following services will be offline and unavailable:

  • ArmorPoint SIEM Platform
  • ArmorPoint Mobile App access
  • Log collection

We are working diligently to minimize disruption and will restore these services as soon as the move is complete.

Services That Will Remain Operational

Your security remains our top priority. The following services will not be affected:

  • Security Monitoring & Incident Response: Our team will continue to monitor and respond to threats in real-time by leveraging EDR access.
  • EDR Monitoring: EDR monitoring will remain fully operational, continuing to collect data and detect threats.